CONSTRUCTION ROADMAP & TIMELINE

Residential Project Planner & Milestones

Track the sequential stages of your home construction, duration schedules, critical quality inspections, and material readiness checkpoints across 34 scheduled weeks.

PROJECT SCHEDULE PROGRESS
9% Completed
TOTAL DURATION
34 Weeks (~8.5 Mos)
COMPLETED STAGES
1 of 8

1. Site Mobilization & Earthwork Excavation

Site Preparation · Duration: 3 Weeks
STAGE COMPLETED

Clearing site vegetation, soil leveling, layout demarcation with builder's string, and foundation trench excavation to firm bearing strata.

PRIMARY PROCUREMENT REQUIREMENTMarking chalk, anti-termite chemical, boundary sheets
CRITICAL QUALITY INSPECTIONVerify site setback distances and municipal benchmark coordinates.

2. Foundation & Substructure Casting

Substructure · Duration: 4 Weeks
IN PENDING QUEUE

Plain Cement Concrete (PCC) bed, footing rebar cage installation, column starter casting, plinth beam tying, and compacted backfilling.

PRIMARY PROCUREMENT REQUIREMENTOPC 43 Cement, coarse aggregate, 12mm TMT rebar, DPC membrane
CRITICAL QUALITY INSPECTIONEnsure 14 days minimum curing for footing concrete and damp-proof course (DPC).

3. RCC Superstructure Framing & Roof Slab

Structural Core · Duration: 7 Weeks
IN PENDING QUEUE

Reinforced column casting, shuttering staging, beam cage tying, slab steel laying with cover blocks, and monolithic concrete casting.

PRIMARY PROCUREMENT REQUIREMENTOPC 53 Cement, Fe 550D TMT rebar, shuttering ply, M25 ready mix
CRITICAL QUALITY INSPECTIONCube compression test at 7 and 28 days (IS 516); zero desuttering before 21 days for slabs.

4. Brickwork, Masonry & AAC Partitions

Enclosure · Duration: 4 Weeks
IN PENDING QUEUE

Constructing 9-inch exterior structural perimeter walls and 4.5-inch interior partition dividing walls with lintel bands over openings.

PRIMARY PROCUREMENT REQUIREMENTRed clay bricks / AAC blocks, masonry cement mortar 1:6
CRITICAL QUALITY INSPECTIONRake mortar joints to 10mm depth while wet to ensure keying for wall plaster.

5. Concealed MEP (Electrical & Plumbing)

Services · Duration: 3 Weeks
IN PENDING QUEUE

Wall chasing, conduit routing, electrical modular backbox embedding, plumbing drainage drops, and concealed water pipeline layout.

PRIMARY PROCUREMENT REQUIREMENTHeavy-duty PVC electrical conduits, CPVC / UPVC water supply pipes
CRITICAL QUALITY INSPECTIONPerform pneumatic/hydraulic pressure testing at 10 kg/cm² for 24 hours prior to concealing pipes.

6. Internal & External Plastering & Waterproofing

Protection & Finishes · Duration: 5 Weeks
IN PENDING QUEUE

Application of 12mm internal cement plaster, 20mm double-coat external sponge plaster, and polymeric elastomeric waterproofing of wet areas.

PRIMARY PROCUREMENT REQUIREMENTFine plaster sand, OPC 43, 2K acrylic waterproofing polymer
CRITICAL QUALITY INSPECTIONWater test sunken bathrooms and terraces for 72 hours without leakage.

7. Flooring, Tiling & Joinery Framing

Surfaces · Duration: 4 Weeks
IN PENDING QUEUE

Bedding mortar screed, tile adhesive application, floor tile leveling, marble door frames, and door/window shutter fixing.

PRIMARY PROCUREMENT REQUIREMENTVitrified tiles, granite sills, polymer tile adhesive, IS 710 marine ply
CRITICAL QUALITY INSPECTIONCheck zero hollow sound on vitrified tiles with rubber mallet tapping audit.

8. Painting, Sanitary Fixtures & Final Handover

Handover · Duration: 4 Weeks
IN PENDING QUEUE

Two coats of wall putty, primer sealing, 2 coats of premium emulsion, electrical switch fitting, sanitary fixture connection, and deep site cleaning.

PRIMARY PROCUREMENT REQUIREMENTAcrylic primer, low-VOC emulsion, CP sanitaryware, switch plates
CRITICAL QUALITY INSPECTIONEnsure moisture meter reads under 12% in plaster before applying first paint coat.